Project Management Software - Critical Path Planning with PlanBee for easy schedules, PERT and Gantt chartsThis is just one of the formats available as output for the house construction project plan example included with PlanBee (Gantt bar and PERT chart outputs are also produced, as well as comprehensive reports). With that example, all you have to do is insert your own project start date and adjust any of the the task durations to your own preference.
For more details about PlanBee click here.
More information: Project Management Software - Critical Path Planning with PlanBee for easy schedules, PERT and Gantt charts Buy
Now: Project Management Software - Critical Path Planning with PlanBee for easy schedules, PERT and Gantt charts Download free trial: Project Management Software - Critical Path Planning with PlanBee for easy schedules, PERT and Gantt charts

Custom House Construction Project Plan

Fred's Construction Company

Project Start: 12-May-2004      Project Finish: 27-Apr-2005

Task NameDurationStartFinishPrecedents
Contracts12-May-200412-May-2004
Supply Lot Sale Agreement 0 days12-May-200412-May-2004
Supply Construction Agreement 0 days12-May-200412-May-2004
Supply Contract Plans 0 days12-May-200412-May-2004Supply Construction Agreement
Supply Contract Specifications 0 days12-May-200412-May-2004Supply Construction Agreement
Supply Contract Site Plan 0 days12-May-200412-May-2004Supply Construction Agreement
Secure Financing 0 days12-May-200412-May-2004
Construction Loan Settlement 0 days12-May-200412-May-2004Secure Financing
Document Review & Revision12-May-200416-Jun-2004
Review & Finalize Plans 15 days12-May-200402-Jun-2004Supply Contract Plans, Supply Lot Sale Agreement, Supply Construction Agreement, Supply Contract Specifications, Supply Contract Site Plan, Construction Loan Settlement
Review & Finalize Specifications 20 days12-May-200409-Jun-2004Supply Contract Specifications
Review & Finalize Site Plan 1 day02-Jun-200403-Jun-2004Supply Contract Site Plan, Review & Finalize Plans
Print Construction Drawings 5 days09-Jun-200416-Jun-2004Review & Finalize Plans, Review & Finalize Specifications, Review & Finalize Site Plan
Approve Revised Plans 0 days16-Jun-200416-Jun-2004Print Construction Drawings
Approve Revised Specifications 0 days16-Jun-200416-Jun-2004Print Construction Drawings
Approve Revised Site Plan 0 days16-Jun-200416-Jun-2004Print Construction Drawings
Bids & Contracts16-Jun-200420-Jul-2004
Make Copies of Plans 3 days16-Jun-200421-Jun-2004Approve Revised Plans, Print Construction Drawings
Make Copies of Specifications 2 days16-Jun-200418-Jun-2004Approve Revised Specifications
Distribute Plans & Specifications 1 day21-Jun-200422-Jun-2004Make Copies of Plans, Make Copies of Specifications
Receive Bids 10 days22-Jun-200406-Jul-2004Distribute Plans & Specifications
Review Bids 5 days06-Jul-200413-Jul-2004Receive Bids
Execute Subcontractor Agreements 5 days13-Jul-200420-Jul-2004Review Bids
Grading & Building Permits16-Jun-200402-Aug-2004
Schedule lot stake-out 1 day16-Jun-200417-Jun-2004Print Construction Drawings
Stake lot 1 day21-Jun-200422-Jun-2004Schedule lot stake-out
File Grading Permit Application 1 day16-Jun-200417-Jun-2004Approve Revised Site Plan
File Building Permit Application 3 days16-Jun-200421-Jun-2004Approve Revised Plans, Approve Revised Specifications, Approve Revised Site Plan
Post Lot Identification 1 day22-Jun-200423-Jun-2004Stake lot, File Grading Permit Application, File Building Permit Application
Meet Sed. Control Insp. 1 day23-Jun-200424-Jun-2004File Grading Permit Application, Stake lot, Post Lot Identification
Walk Lot w/ Owner 1 day20-Jul-200421-Jul-2004Meet Sed. Control Insp., Execute Subcontractor Agreements
Install Construction Entrance 1 day21-Jul-200422-Jul-2004Meet Sed. Control Insp., Walk Lot w/ Owner
Install Sediment Controls 2 days21-Jul-200423-Jul-2004Meet Sed. Control Insp., Walk Lot w/ Owner
Sediment Control Insp. 1 day23-Jul-200426-Jul-2004Install Construction Entrance, Install Sediment Controls
Grading Permit Issued 1 day26-Jul-200427-Jul-2004Sediment Control Insp.
Municipal Permit Process 10 days21-Jun-200405-Jul-2004File Building Permit Application, File Grading Permit Application
Building Permit Approved 1 day27-Jul-200428-Jul-2004Municipal Permit Process, Grading Permit Issued
Pay Permit Fees and Taxes 1 day30-Jul-200402-Aug-2004Building Permit Approved
Building Permit Issued 0 days02-Aug-200402-Aug-2004Pay Permit Fees and Taxes
Site Work27-Jul-200409-Aug-2004
Clear Lot 3 days27-Jul-200430-Jul-2004Grading Permit Issued
Strip Topsoil & Stockpile 1 day02-Aug-200403-Aug-2004Clear Lot, Building Permit Issued
Stake Lot for Excavation 1 day03-Aug-200404-Aug-2004Clear Lot, Strip Topsoil & Stockpile
Rough grade lot 1 day04-Aug-200405-Aug-2004Clear Lot, Stake Lot for Excavation
Excavate for foundation 2 days05-Aug-200409-Aug-2004Building Permit Approved, Stake Lot for Excavation, Clear Lot, Rough grade lot
Foundation09-Aug-200410-Sep-2004
Layout footings 1 day09-Aug-200410-Aug-2004Excavate for foundation
Dig Footings & Install Reinforcing 1 day10-Aug-200411-Aug-2004Layout footings
Footing Inspection 0 days11-Aug-200411-Aug-2004Dig Footings & Install Reinforcing
Pour footings 1 day11-Aug-200412-Aug-2004Footing Inspection
Pin Footings 1 day12-Aug-200413-Aug-2004Pour footings
Stock Block, Mortar, Sand 1 day13-Aug-200416-Aug-2004Pin Footings
Build Block Foundation 15 days16-Aug-200406-Sep-2004Pin Footings, Stock Block, Mortar, Sand, Footing Inspection
Foundation Certification 0 days06-Sep-200406-Sep-2004Build Block Foundation
Fill Block Cores w/ Concrete 1 day06-Sep-200407-Sep-2004Build Block Foundation, Foundation Certification
Steel Delivery 1 day07-Sep-200408-Sep-2004Fill Block Cores w/ Concrete
Set Lintels, Bolts, Cap Block 2 days08-Sep-200410-Sep-2004Steel Delivery
Lumber Delivery 1 day07-Sep-200408-Sep-2004Fill Block Cores w/ Concrete, Stake Lot for Excavation
Waterproofing and Drain Tile 1 day08-Sep-200409-Sep-2004Lumber Delivery
Rough Carpentry10-Sep-200427-Oct-2004
Set Steel 1 day10-Sep-200413-Sep-2004Set Lintels, Bolts, Cap Block, Lumber Delivery
1st Floor Deck Framing 4 days13-Sep-200417-Sep-2004Set Steel
1st Floor Wall Framing 4 days17-Sep-200423-Sep-20041st Floor Deck Framing
2nd Floor Deck Framing 2 days23-Sep-200427-Sep-20041st Floor Wall Framing
2nd Floor Wall Framing 3 days27-Sep-200430-Sep-20042nd Floor Deck Framing
Set Roof Trusses 2 days30-Sep-200404-Oct-20042nd Floor Wall Framing
Frame Roof 7 days04-Oct-200413-Oct-2004Set Roof Trusses
Install Roof Plywood 5 days13-Oct-200420-Oct-2004Frame Roof
Install Windows & Doors 2 days25-Oct-200427-Oct-2004Install Roof Plywood, Roofing Paper Installed
Frame Basement 3 days21-Oct-200426-Oct-2004Frame Roof, Pour Basement Slab
Concrete Slabs14-Oct-200426-Oct-2004
Basement Slab Preparation 2 days14-Oct-200418-Oct-20041st Floor Deck Framing, Plumbing Sub-slab, Waterproofing and Drain Tile, HVAC Layout & Measure
Termite Treatment Basement Slab 1 day18-Oct-200419-Oct-2004Basement Slab Preparation
Slab Inspection 1 day19-Oct-200420-Oct-2004Termite Treatment Basement Slab
Pour Basement Slab 1 day20-Oct-200421-Oct-2004Slab Inspection
Prep Garage Slab 1 day21-Oct-200422-Oct-2004Pour Basement Slab
Termite Treatment Garage Slab 1 day22-Oct-200425-Oct-2004Prep Garage Slab
Pour Garage Slab 1 day25-Oct-200426-Oct-2004Termite Treatment Garage Slab
H.V.A.C.13-Oct-200404-Nov-2004
HVAC Layout & Measure 1 day13-Oct-200414-Oct-2004Frame Roof
HVAC Rough-in 5 days25-Oct-200401-Nov-2004HVAC Layout & Measure, Roofing Paper Installed
HVAC Set Indoor Units 2 days01-Nov-200403-Nov-2004Pour Basement Slab, HVAC Rough-in
HVAC Temporary Heat 2 days02-Nov-200404-Nov-2004Install Electric Service Panel
Plumbing Rough-in17-Sep-200409-Nov-2004
Plumbing Sub-slab 2 days17-Sep-200421-Sep-20041st Floor Deck Framing
Plumbing Layout 1 day01-Nov-200402-Nov-2004Plumbing Sub-slab, HVAC Rough-in
Plumbing rough-in 5 days02-Nov-200409-Nov-2004Plumbing Layout, Municipal Plumbing Sub-slab Inspection
Municipal Plumbing Sub-slab Inspection 0 days21-Sep-200421-Sep-2004Plumbing Sub-slab
Municipal Plumbing Rough-in Inspection 0 days09-Nov-200409-Nov-2004Plumbing rough-in
Electric Rough-in27-Oct-200423-Nov-2004
Set Electric Boxes 2 days27-Oct-200429-Oct-2004Install Windows & Doors
Install Electric Service Panel 2 days29-Oct-200402-Nov-2004Set Electric Boxes
Electrical Walk-through 1 day02-Nov-200403-Nov-2004Install Electric Service Panel
Electrical Rough-wire 14 days03-Nov-200423-Nov-2004Electrical Walk-through
Specialty Rough-ins23-Nov-200407-Dec-2004
Central Vacuum Rough-in 5 days23-Nov-200430-Nov-2004Electrical Rough-wire
Alarm System Rough-in 5 days23-Nov-200430-Nov-2004Electrical Rough-wire
Telephone System Rough-in 5 days23-Nov-200430-Nov-2004Electrical Rough-wire
Television System Rough-in 5 days30-Nov-200407-Dec-2004Telephone System Rough-in
Audio Visual Rough-in 5 days23-Nov-200430-Nov-2004Electrical Rough-wire
Municipal Electrical inspection 0 days23-Nov-200423-Nov-2004Electrical Rough-wire
Municipal Framing Inspection 0 days24-Nov-200424-Nov-2004Municipal Plumbing Rough-in Inspection, Municipal Electrical inspection
Roofing20-Oct-200424-Jan-2005
Roofing Paper Installed 3 days20-Oct-200425-Oct-2004Install Roof Plywood
Stock Roof Shingles 1 day25-Oct-200426-Oct-2004Roofing Paper Installed
Install Roof Shingles 7 days13-Jan-200524-Jan-2005Stock Roof Shingles, Brick Veneer
Exterior Finishes27-Oct-200413-Jan-2005
Siding 3 days27-Oct-200401-Nov-2004Install Windows & Doors
Exterior Trim 7 days01-Nov-200410-Nov-2004Siding
Brick Arch Forms 1 day10-Nov-200411-Nov-2004Exterior Trim
Brick Veneer 45 days11-Nov-200413-Jan-2005Brick Arch Forms
Insulation24-Nov-200401-Dec-2004
Caulk & Air Seal 1 day24-Nov-200425-Nov-2004Municipal Framing Inspection
Draft & Fire Stop 1 day25-Nov-200426-Nov-2004Caulk & Air Seal
Batt Insulation 3 days26-Nov-200401-Dec-2004Caulk & Air Seal, Draft & Fire Stop
Municipal Insulation Inspection 0 days01-Dec-200401-Dec-2004Batt Insulation
Drywall01-Dec-200406-Jan-2005
Stock Drywall 1 day01-Dec-200402-Dec-2004Municipal Insulation Inspection, HVAC Temporary Heat
Hang Drywall 5 days02-Dec-200409-Dec-2004Stock Drywall
Remove Scrap Drywall 1 day09-Dec-200410-Dec-2004Hang Drywall
Tape and Finish Drywall 15 days10-Dec-200431-Dec-2004Hang Drywall, Remove Scrap Drywall
Sand Drywall 1 day31-Dec-200403-Jan-2005Tape and Finish Drywall
Drywall Point-up 3 days03-Jan-200506-Jan-2005Sand Drywall
Floor Finishes07-Jan-200511-Apr-2005
Ceramic Tile 15 days07-Jan-200528-Jan-2005Prime Paint Drywall
Install Hardwood Floor 4 days23-Mar-200529-Mar-2005Finish Coat Drywall
Sand, Stain, Seal Hardwood 5 days29-Mar-200505-Apr-2005Install Hardwood Floor
Install Carpet 4 days05-Apr-200511-Apr-2005Sand, Stain, Seal Hardwood
Final Coat Hardwood 2 days05-Apr-200507-Apr-2005Sand, Stain, Seal Hardwood
Paint03-Jan-200525-Mar-2005
Prep Drywall for Prime Coat 2 days03-Jan-200505-Jan-2005Sand Drywall, HVAC Set Indoor Units
Prime Paint Drywall 2 days05-Jan-200507-Jan-2005Prep Drywall for Prime Coat
Prep Trim for Prime Coat 2 days17-Jan-200519-Jan-2005Prime Paint Drywall, Install Interior Doors
Prime Trim 2 days19-Jan-200521-Jan-2005Prep Trim for Prime Coat
Finish Coat Trim 10 days17-Feb-200503-Mar-2005Prime Trim, 1st Punch-out Interior Trim, Install Grills & Registers for Paint
Finish Coat Drywall 14 days03-Mar-200523-Mar-2005Finish Coat Trim, Drywall Point-up
Caulk Exterior Windows & Doors 1 day23-Mar-200524-Mar-2005Finish Coat Drywall, Exterior Trim
Finish Coat Exterior Trim & Siding 1 day24-Mar-200525-Mar-2005Caulk Exterior Windows & Doors
Interior Trim07-Jan-200517-Feb-2005
Interior Trim Delivery 1 day07-Jan-200510-Jan-2005Prime Paint Drywall
Install Interior Doors 5 days10-Jan-200517-Jan-2005Interior Trim Delivery
Install Interior Trim 15 days17-Jan-200507-Feb-2005Install Interior Doors
Install Cabinetry 5 days07-Feb-200514-Feb-2005Install Interior Trim
Install Appliances 1 day14-Feb-200515-Feb-2005Install Cabinetry, Central Vacuum Rough-in, Alarm System Rough-in, Audio Visual Rough-in, Television System Rough-in
1st Punch-out Interior Trim 2 days15-Feb-200517-Feb-2005Install Appliances, Prime Trim
H.V.A.C. Trim03-Jan-200517-Jan-2005
Install Grills & Registers for Paint 1 day03-Jan-200504-Jan-2005Sand Drywall
Set Outdoor Units 1 day14-Jan-200517-Jan-2005Rough Final Grade
Plumbing Trim29-Mar-200505-Apr-2005
Set Fixtures 4 days29-Mar-200504-Apr-2005Ceramic Tile, Install Hardwood Floor, Finish Coat Drywall, Install Cabinetry
Connect Appliances 1 day04-Apr-200505-Apr-2005Set Fixtures, Install Appliances
Municipal Final Plumbing Inspection 0 days05-Apr-200505-Apr-2005Connect Appliances
Exterior Landscaping13-Jan-200528-Feb-2005
Rough Final Grade 1 day13-Jan-200514-Jan-2005Brick Veneer
Patios 7 days14-Jan-200525-Jan-2005Rough Final Grade
Porches 5 days25-Jan-200501-Feb-2005Patios
Sidewalks 7 days01-Feb-200510-Feb-2005Porches
Decks 7 days10-Feb-200521-Feb-2005Sidewalks
Driveways 2 days21-Feb-200523-Feb-2005Rough Final Grade, Decks
Final Grade and Seed 3 days23-Feb-200528-Feb-2005Driveways, Patios, Porches, Sidewalks, Decks, Set Outdoor Units
Electrical Final Trim07-Jan-200516-Feb-2005
Switch & Plug 2 days07-Jan-200511-Jan-2005Prime Paint Drywall, Electrical Rough-wire
Install Fixtures 1 day11-Jan-200512-Jan-2005Switch & Plug
Connect Appliances 1 day15-Feb-200516-Feb-2005Install Fixtures, Install Appliances
Hardware23-Mar-200514-Apr-2005
Door Hardware 2 days23-Mar-200525-Mar-2005Finish Coat Trim, Finish Coat Drywall, Install Interior Doors
Bath Hardware 2 days23-Mar-200525-Mar-2005Finish Coat Drywall, Finish Coat Trim
Mirrors 5 days25-Mar-200501-Apr-2005Bath Hardware
Shower Doors 10 days25-Mar-200508-Apr-2005Bath Hardware
Final Building Inspection 0 days11-Apr-200511-Apr-2005Shower Doors, Finish Coat Trim, Finish Coat Exterior Trim & Siding, Connect Appliances, Pour Garage Slab, Install Carpet, Mirrors, Door Hardware, Connect Appliances, Final Grade and Seed, Install Roof Shingles
Use & Occupancy Certificate 0 days14-Apr-200514-Apr-2005Municipal Final Plumbing Inspection, Final Building Inspection
First Walk-thru 0 days14-Apr-200514-Apr-2005Use & Occupancy Certificate
Final Punch-out14-Apr-200527-Apr-2005
Punch Out Walk-thru List 4 days14-Apr-200520-Apr-2005First Walk-thru
Trim and Adjust Doors 2 days20-Apr-200522-Apr-2005Punch Out Walk-thru List
Paint Touch-up 3 days22-Apr-200527-Apr-2005Trim and Adjust Doors
Cleaning23-Mar-200527-Apr-2005
Windows 3 days23-Mar-200528-Mar-2005Finish Coat Trim, Finish Coat Drywall
Rough Clean 3 days28-Mar-200531-Mar-2005Windows
Final Clean 2 days22-Apr-200526-Apr-2005Rough Clean, Trim and Adjust Doors
Final Walk-through 0 days26-Apr-200526-Apr-2005Final Clean, Use & Occupancy Certificate
Move-in 0 days27-Apr-200527-Apr-2005Final Walk-through