| Task Name | Duration | Start | Latest Start | Finish | Latest Finish |
| Contracts | | 04-Jun-2012 | 05-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
| Supply Lot Sale Agreement | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
| Supply Construction Agreement | 0 days | 04-Jun-2012 | 05-Jun-2012 | 04-Jun-2012 | 05-Jun-2012 |
| Supply Contract Plans | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
| Supply Contract Specifications | 0 days | 04-Jun-2012 | 05-Jun-2012 | 04-Jun-2012 | 05-Jun-2012 |
| Supply Contract Site Plan | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
| Secure Financing | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
| Construction Loan Settlement | 0 days | 04-Jun-2012 | 11-Jun-2012 | 04-Jun-2012 | 11-Jun-2012 |
| Document Review & Revision | | 04-Jun-2012 | 05-Jun-2012 | 09-Jul-2012 | 01-Aug-2012 |
| Review & Finalize Plans | 15 days | 04-Jun-2012 | 11-Jun-2012 | 25-Jun-2012 | 02-Jul-2012 |
| Review & Finalize Specifications | 20 days | 04-Jun-2012 | 05-Jun-2012 | 02-Jul-2012 | 03-Jul-2012 |
| Review & Finalize Site Plan | 1 day | 25-Jun-2012 | 02-Jul-2012 | 26-Jun-2012 | 03-Jul-2012 |
| Print Construction Drawings | 5 days | 02-Jul-2012 | 03-Jul-2012 | 09-Jul-2012 | 10-Jul-2012 |
| Approve Revised Plans | 0 days | 09-Jul-2012 | 10-Jul-2012 | 09-Jul-2012 | 10-Jul-2012 |
| Approve Revised Specifications | 0 days | 09-Jul-2012 | 11-Jul-2012 | 09-Jul-2012 | 11-Jul-2012 |
| Approve Revised Site Plan | 0 days | 09-Jul-2012 | 01-Aug-2012 | 09-Jul-2012 | 01-Aug-2012 |
| Bids & Contracts | | 09-Jul-2012 | 10-Jul-2012 | 10-Aug-2012 | 13-Aug-2012 |
| Make Copies of Plans | 3 days | 09-Jul-2012 | 10-Jul-2012 | 12-Jul-2012 | 13-Jul-2012 |
| Make Copies of Specifications | 2 days | 09-Jul-2012 | 11-Jul-2012 | 11-Jul-2012 | 13-Jul-2012 |
| Distribute Plans & Specifications | 1 day | 12-Jul-2012 | 13-Jul-2012 | 13-Jul-2012 | 16-Jul-2012 |
| Receive Bids | 10 days | 13-Jul-2012 | 16-Jul-2012 | 27-Jul-2012 | 30-Jul-2012 |
| Review Bids | 5 days | 27-Jul-2012 | 30-Jul-2012 | 03-Aug-2012 | 06-Aug-2012 |
| Execute Subcontractor Agreements | 5 days | 03-Aug-2012 | 06-Aug-2012 | 10-Aug-2012 | 13-Aug-2012 |
| Grading & Building Permits | | 09-Jul-2012 | 01-Aug-2012 | 23-Aug-2012 | 24-Aug-2012 |
| Schedule lot stake-out | 1 day | 09-Jul-2012 | 02-Aug-2012 | 10-Jul-2012 | 03-Aug-2012 |
| Stake lot | 1 day | 13-Jul-2012 | 08-Aug-2012 | 16-Jul-2012 | 09-Aug-2012 |
| File Grading Permit Application | 1 day | 09-Jul-2012 | 03-Aug-2012 | 10-Jul-2012 | 06-Aug-2012 |
| File Building Permit Application | 3 days | 09-Jul-2012 | 01-Aug-2012 | 12-Jul-2012 | 06-Aug-2012 |
| Post Lot Identification | 1 day | 16-Jul-2012 | 09-Aug-2012 | 17-Jul-2012 | 10-Aug-2012 |
| Meet Sed. Control Insp. | 1 day | 17-Jul-2012 | 10-Aug-2012 | 18-Jul-2012 | 13-Aug-2012 |
| Walk Lot w/ Owner | 1 day | 10-Aug-2012 | 13-Aug-2012 | 13-Aug-2012 | 14-Aug-2012 |
| Install Construction Entrance | 1 day | 13-Aug-2012 | 15-Aug-2012 | 14-Aug-2012 | 16-Aug-2012 |
| Install Sediment Controls | 2 days | 13-Aug-2012 | 14-Aug-2012 | 15-Aug-2012 | 16-Aug-2012 |
| Sediment Control Insp. | 1 day | 15-Aug-2012 | 16-Aug-2012 | 16-Aug-2012 | 17-Aug-2012 |
| Grading Permit Issued | 1 day | 16-Aug-2012 | 17-Aug-2012 | 17-Aug-2012 | 20-Aug-2012 |
| Municipal Permit Process | 10 days | 12-Jul-2012 | 06-Aug-2012 | 26-Jul-2012 | 20-Aug-2012 |
| Building Permit Approved | 1 day | 17-Aug-2012 | 20-Aug-2012 | 20-Aug-2012 | 21-Aug-2012 |
| Pay Permit Fees and Excise Taxes | 1 day | 22-Aug-2012 | 23-Aug-2012 | 23-Aug-2012 | 24-Aug-2012 |
| Building Permit Issued | 0 days | 23-Aug-2012 | 24-Aug-2012 | 23-Aug-2012 | 24-Aug-2012 |
| Site Work | | 17-Aug-2012 | 21-Aug-2012 | 30-Aug-2012 | 31-Aug-2012 |
| Clear Lot | 3 days | 17-Aug-2012 | 21-Aug-2012 | 22-Aug-2012 | 24-Aug-2012 |
| Strip Topsoil & Stockpile | 1 day | 23-Aug-2012 | 24-Aug-2012 | 24-Aug-2012 | 27-Aug-2012 |
| Stake Lot for Excavation | 1 day | 24-Aug-2012 | 27-Aug-2012 | 27-Aug-2012 | 28-Aug-2012 |
| Rough grade lot | 1 day | 27-Aug-2012 | 28-Aug-2012 | 28-Aug-2012 | 29-Aug-2012 |
| Excavate for foundation | 2 days | 28-Aug-2012 | 29-Aug-2012 | 30-Aug-2012 | 31-Aug-2012 |
| Foundation | | 30-Aug-2012 | 31-Aug-2012 | 03-Oct-2012 | 16-Jan-2013 |
| Layout footings | 1 day | 30-Aug-2012 | 31-Aug-2012 | 31-Aug-2012 | 03-Sep-2012 |
| Dig Footings & Install Reinforcing | 1 day | 31-Aug-2012 | 03-Sep-2012 | 03-Sep-2012 | 04-Sep-2012 |
| Footing Inspection | 0 days | 03-Sep-2012 | 04-Sep-2012 | 03-Sep-2012 | 04-Sep-2012 |
| Pour footings | 1 day | 03-Sep-2012 | 04-Sep-2012 | 04-Sep-2012 | 05-Sep-2012 |
| Pin Footings | 1 day | 04-Sep-2012 | 05-Sep-2012 | 05-Sep-2012 | 06-Sep-2012 |
| Stock Block, Mortar, Sand | 1 day | 05-Sep-2012 | 06-Sep-2012 | 06-Sep-2012 | 07-Sep-2012 |
| Build Block Foundation | 15 days | 06-Sep-2012 | 07-Sep-2012 | 27-Sep-2012 | 28-Sep-2012 |
| Foundation Certification | 0 days | 27-Sep-2012 | 28-Sep-2012 | 27-Sep-2012 | 28-Sep-2012 |
| Fill Block Cores w/ Concrete | 1 day | 27-Sep-2012 | 28-Sep-2012 | 28-Sep-2012 | 01-Oct-2012 |
| Steel Delivery | 1 day | 28-Sep-2012 | 01-Oct-2012 | 01-Oct-2012 | 02-Oct-2012 |
| Set Lintels, Bolts, Cap Block | 2 days | 01-Oct-2012 | 02-Oct-2012 | 03-Oct-2012 | 04-Oct-2012 |
| Lumber Delivery | 1 day | 28-Sep-2012 | 03-Oct-2012 | 01-Oct-2012 | 04-Oct-2012 |
| Waterproofing and Drain Tile | 1 day | 01-Oct-2012 | 15-Jan-2013 | 02-Oct-2012 | 16-Jan-2013 |
| Rough Carpentry | | 04-Jun-2012 | 04-Oct-2012 | 19-Nov-2012 | 17-May-2013 |
| Set Steel | 1 day | 03-Oct-2012 | 04-Oct-2012 | 04-Oct-2012 | 05-Oct-2012 |
| 1st Floor Deck Framing | 4 days | 04-Oct-2012 | 05-Oct-2012 | 10-Oct-2012 | 11-Oct-2012 |
| 1st Floor Wall Framing | 4 days | 10-Oct-2012 | 11-Oct-2012 | 16-Oct-2012 | 17-Oct-2012 |
| 2nd Floor Deck Framing | 2 days | 16-Oct-2012 | 17-Oct-2012 | 18-Oct-2012 | 19-Oct-2012 |
| 2nd Floor Wall Framing | 3 days | 18-Oct-2012 | 19-Oct-2012 | 23-Oct-2012 | 24-Oct-2012 |
| Set Roof Trusses | 2 days | 23-Oct-2012 | 24-Oct-2012 | 25-Oct-2012 | 26-Oct-2012 |
| Frame Roof | 7 days | 25-Oct-2012 | 26-Oct-2012 | 05-Nov-2012 | 06-Nov-2012 |
| Install Roof Plywood | 5 days | 05-Nov-2012 | 06-Nov-2012 | 12-Nov-2012 | 13-Nov-2012 |
| Install Windows & Doors | 2 days | 15-Nov-2012 | 16-Nov-2012 | 19-Nov-2012 | 20-Nov-2012 |
| Frame Basement | 3 days | 13-Nov-2012 | 14-May-2013 | 16-Nov-2012 | 17-May-2013 |
| REMOVE | 2 days | 04-Jun-2012 | 15-May-2013 | 06-Jun-2012 | 17-May-2013 |
| Concrete Slabs | | 06-Nov-2012 | 16-Jan-2013 | 16-Nov-2012 | 03-May-2013 |
| Basement Slab Preparation | 2 days | 06-Nov-2012 | 16-Jan-2013 | 08-Nov-2012 | 18-Jan-2013 |
| Termite Treatment Basement Slab | 1 day | 08-Nov-2012 | 18-Jan-2013 | 09-Nov-2012 | 21-Jan-2013 |
| Slab Inspection | 1 day | 09-Nov-2012 | 21-Jan-2013 | 12-Nov-2012 | 22-Jan-2013 |
| Pour Basement Slab | 1 day | 12-Nov-2012 | 22-Jan-2013 | 13-Nov-2012 | 23-Jan-2013 |
| Prep Garage Slab | 1 day | 13-Nov-2012 | 30-Apr-2013 | 14-Nov-2012 | 01-May-2013 |
| Termite Treatment Garage Slab | 1 day | 14-Nov-2012 | 01-May-2013 | 15-Nov-2012 | 02-May-2013 |
| Pour Garage Slab | 1 day | 15-Nov-2012 | 02-May-2013 | 16-Nov-2012 | 03-May-2013 |
| H.V.A.C. | | 05-Nov-2012 | 29-Nov-2012 | 27-Nov-2012 | 25-Jan-2013 |
| HVAC Layout & Measure | 1 day | 05-Nov-2012 | 29-Nov-2012 | 06-Nov-2012 | 30-Nov-2012 |
| HVAC Rough-in | 5 days | 15-Nov-2012 | 30-Nov-2012 | 22-Nov-2012 | 07-Dec-2012 |
| HVAC Set Indoor Units | 2 days | 22-Nov-2012 | 23-Jan-2013 | 26-Nov-2012 | 25-Jan-2013 |
| HVAC Temporary Heat | 2 days | 23-Nov-2012 | 21-Dec-2012 | 27-Nov-2012 | 25-Dec-2012 |
| Plumbing Rough-in | | 10-Oct-2012 | 05-Dec-2012 | 30-Nov-2012 | 17-Dec-2012 |
| Plumbing Sub-slab | 2 days | 10-Oct-2012 | 05-Dec-2012 | 12-Oct-2012 | 07-Dec-2012 |
| Plumbing Layout | 1 day | 22-Nov-2012 | 07-Dec-2012 | 23-Nov-2012 | 10-Dec-2012 |
| Plumbing rough-in | 5 days | 23-Nov-2012 | 10-Dec-2012 | 30-Nov-2012 | 17-Dec-2012 |
| Municipal Plumbing Sub-slab Inspection | 0 days | 12-Oct-2012 | 10-Dec-2012 | 12-Oct-2012 | 10-Dec-2012 |
| Municipal Plumbing Rough-in Inspection | 0 days | 30-Nov-2012 | 17-Dec-2012 | 30-Nov-2012 | 17-Dec-2012 |
| Electric Rough-in | | 19-Nov-2012 | 20-Nov-2012 | 14-Dec-2012 | 17-Dec-2012 |
| Set Electric Boxes | 2 days | 19-Nov-2012 | 20-Nov-2012 | 21-Nov-2012 | 22-Nov-2012 |
| Install Electric Service Panel | 2 days | 21-Nov-2012 | 22-Nov-2012 | 23-Nov-2012 | 26-Nov-2012 |
| Electrical Walk-through | 1 day | 23-Nov-2012 | 26-Nov-2012 | 26-Nov-2012 | 27-Nov-2012 |
| Electrical Rough-wire | 14 days | 26-Nov-2012 | 27-Nov-2012 | 14-Dec-2012 | 17-Dec-2012 |
| Specialty Rough-ins | | 14-Dec-2012 | 17-Dec-2012 | 28-Dec-2012 | 08-Mar-2013 |
| Central Vacuum Rough-in | 5 days | 14-Dec-2012 | 01-Mar-2013 | 21-Dec-2012 | 08-Mar-2013 |
| Alarm System Rough-in | 5 days | 14-Dec-2012 | 01-Mar-2013 | 21-Dec-2012 | 08-Mar-2013 |
| Telephone System Rough-in | 5 days | 14-Dec-2012 | 22-Feb-2013 | 21-Dec-2012 | 01-Mar-2013 |
| Television System Rough-in | 5 days | 21-Dec-2012 | 01-Mar-2013 | 28-Dec-2012 | 08-Mar-2013 |
| Audio Visual Rough-in | 5 days | 14-Dec-2012 | 01-Mar-2013 | 21-Dec-2012 | 08-Mar-2013 |
| Municipal Electrical inspection | 0 days | 14-Dec-2012 | 17-Dec-2012 | 14-Dec-2012 | 17-Dec-2012 |
| Municipal Framing Inspection | 0 days | 17-Dec-2012 | 18-Dec-2012 | 17-Dec-2012 | 18-Dec-2012 |
| Roofing | | 12-Nov-2012 | 13-Nov-2012 | 14-Feb-2013 | 03-May-2013 |
| Roofing Paper Installed | 3 days | 12-Nov-2012 | 13-Nov-2012 | 15-Nov-2012 | 16-Nov-2012 |
| Stock Roof Shingles | 1 day | 15-Nov-2012 | 23-Apr-2013 | 16-Nov-2012 | 24-Apr-2013 |
| Install Roof Shingles | 7 days | 05-Feb-2013 | 24-Apr-2013 | 14-Feb-2013 | 03-May-2013 |
| Exterior Finishes | | 19-Nov-2012 | 01-Jan-2013 | 05-Feb-2013 | 20-Mar-2013 |
| Siding | 3 days | 19-Nov-2012 | 01-Jan-2013 | 22-Nov-2012 | 04-Jan-2013 |
| Exterior Trim | 7 days | 22-Nov-2012 | 04-Jan-2013 | 03-Dec-2012 | 15-Jan-2013 |
| Brick Arch Forms | 1 day | 03-Dec-2012 | 15-Jan-2013 | 04-Dec-2012 | 16-Jan-2013 |
| Brick Veneer | 45 days | 04-Dec-2012 | 16-Jan-2013 | 05-Feb-2013 | 20-Mar-2013 |
| Insulation | | 17-Dec-2012 | 18-Dec-2012 | 24-Dec-2012 | 25-Dec-2012 |
| Caulk & Air Seal | 1 day | 17-Dec-2012 | 18-Dec-2012 | 18-Dec-2012 | 19-Dec-2012 |
| Draft & Fire Stop | 1 day | 18-Dec-2012 | 19-Dec-2012 | 19-Dec-2012 | 20-Dec-2012 |
| Batt Insulation | 3 days | 19-Dec-2012 | 20-Dec-2012 | 24-Dec-2012 | 25-Dec-2012 |
| Municipal Insulation Inspection | 0 days | 24-Dec-2012 | 25-Dec-2012 | 24-Dec-2012 | 25-Dec-2012 |
| Drywall | | 24-Dec-2012 | 25-Dec-2012 | 29-Jan-2013 | 27-Mar-2013 |
| Stock Drywall | 1 day | 24-Dec-2012 | 25-Dec-2012 | 25-Dec-2012 | 26-Dec-2012 |
| Hang Drywall | 5 days | 25-Dec-2012 | 26-Dec-2012 | 01-Jan-2013 | 02-Jan-2013 |
| Remove Scrap Drywall | 1 day | 01-Jan-2013 | 02-Jan-2013 | 02-Jan-2013 | 03-Jan-2013 |
| Tape and Finish Drywall | 15 days | 02-Jan-2013 | 03-Jan-2013 | 23-Jan-2013 | 24-Jan-2013 |
| Sand Drywall | 1 day | 23-Jan-2013 | 24-Jan-2013 | 24-Jan-2013 | 25-Jan-2013 |
| Drywall Point-up | 3 days | 24-Jan-2013 | 22-Mar-2013 | 29-Jan-2013 | 27-Mar-2013 |
| Floor Finishes | | 30-Jan-2013 | 05-Apr-2013 | 02-May-2013 | 17-May-2013 |
| Ceramic Tile | 15 days | 30-Jan-2013 | 05-Apr-2013 | 20-Feb-2013 | 26-Apr-2013 |
| Install Hardwood Floor | 4 days | 15-Apr-2013 | 16-Apr-2013 | 19-Apr-2013 | 22-Apr-2013 |
| Sand, Stain, Seal Hardwood | 5 days | 19-Apr-2013 | 22-Apr-2013 | 26-Apr-2013 | 29-Apr-2013 |
| Install Carpet | 4 days | 26-Apr-2013 | 29-Apr-2013 | 02-May-2013 | 03-May-2013 |
| Final Coat Hardwood | 2 days | 26-Apr-2013 | 15-May-2013 | 30-Apr-2013 | 17-May-2013 |
| Paint | | 24-Jan-2013 | 25-Jan-2013 | 17-Apr-2013 | 03-May-2013 |
| Prep Drywall for Prime Coat | 2 days | 24-Jan-2013 | 25-Jan-2013 | 28-Jan-2013 | 29-Jan-2013 |
| Prime Paint Drywall | 2 days | 28-Jan-2013 | 29-Jan-2013 | 30-Jan-2013 | 31-Jan-2013 |
| Prep Trim for Prime Coat | 2 days | 07-Feb-2013 | 05-Mar-2013 | 11-Feb-2013 | 07-Mar-2013 |
| Prime Trim | 2 days | 11-Feb-2013 | 07-Mar-2013 | 13-Feb-2013 | 11-Mar-2013 |
| Finish Coat Trim | 10 days | 12-Mar-2013 | 13-Mar-2013 | 26-Mar-2013 | 27-Mar-2013 |
| Finish Coat Drywall | 14 days | 26-Mar-2013 | 27-Mar-2013 | 15-Apr-2013 | 16-Apr-2013 |
| Caulk Exterior Windows & Doors | 1 day | 15-Apr-2013 | 01-May-2013 | 16-Apr-2013 | 02-May-2013 |
| Finish Coat Exterior Trim & Siding | 1 day | 16-Apr-2013 | 02-May-2013 | 17-Apr-2013 | 03-May-2013 |
| Interior Trim | | 30-Jan-2013 | 31-Jan-2013 | 12-Mar-2013 | 13-Mar-2013 |
| Interior Trim Delivery | 1 day | 30-Jan-2013 | 31-Jan-2013 | 31-Jan-2013 | 01-Feb-2013 |
| Install Interior Doors | 5 days | 31-Jan-2013 | 01-Feb-2013 | 07-Feb-2013 | 08-Feb-2013 |
| Install Interior Trim | 15 days | 07-Feb-2013 | 08-Feb-2013 | 28-Feb-2013 | 01-Mar-2013 |
| Install Cabinetry | 5 days | 28-Feb-2013 | 01-Mar-2013 | 07-Mar-2013 | 08-Mar-2013 |
| Install Appliances | 1 day | 07-Mar-2013 | 08-Mar-2013 | 08-Mar-2013 | 11-Mar-2013 |
| 1st Punch-out Interior Trim | 2 days | 08-Mar-2013 | 11-Mar-2013 | 12-Mar-2013 | 13-Mar-2013 |
| H.V.A.C. Trim | | 24-Jan-2013 | 12-Mar-2013 | 07-Feb-2013 | 30-Apr-2013 |
| Install Grills & Registers for Paint | 1 day | 24-Jan-2013 | 12-Mar-2013 | 25-Jan-2013 | 13-Mar-2013 |
| Set Outdoor Units | 1 day | 06-Feb-2013 | 29-Apr-2013 | 07-Feb-2013 | 30-Apr-2013 |
| Plumbing Trim | | 19-Apr-2013 | 26-Apr-2013 | 26-Apr-2013 | 03-May-2013 |
| Set Fixtures | 4 days | 19-Apr-2013 | 26-Apr-2013 | 25-Apr-2013 | 02-May-2013 |
| Connect Appliances | 1 day | 25-Apr-2013 | 02-May-2013 | 26-Apr-2013 | 03-May-2013 |
| Municipal Final Plumbing Inspection | 0 days | 26-Apr-2013 | 03-May-2013 | 26-Apr-2013 | 03-May-2013 |
| Exterior Landscaping | | 05-Feb-2013 | 20-Mar-2013 | 21-Mar-2013 | 03-May-2013 |
| Rough Final Grade | 1 day | 05-Feb-2013 | 20-Mar-2013 | 06-Feb-2013 | 21-Mar-2013 |
| Patios | 7 days | 06-Feb-2013 | 21-Mar-2013 | 15-Feb-2013 | 01-Apr-2013 |
| Porches | 5 days | 15-Feb-2013 | 01-Apr-2013 | 22-Feb-2013 | 08-Apr-2013 |
| Sidewalks | 7 days | 22-Feb-2013 | 08-Apr-2013 | 05-Mar-2013 | 17-Apr-2013 |
| Decks | 7 days | 05-Mar-2013 | 17-Apr-2013 | 14-Mar-2013 | 26-Apr-2013 |
| Driveways | 2 days | 14-Mar-2013 | 26-Apr-2013 | 18-Mar-2013 | 30-Apr-2013 |
| Final Grade and Seed | 3 days | 18-Mar-2013 | 30-Apr-2013 | 21-Mar-2013 | 03-May-2013 |
| Electrical Final Trim | | 30-Jan-2013 | 29-Apr-2013 | 11-Mar-2013 | 03-May-2013 |
| Switch & Plug | 2 days | 30-Jan-2013 | 29-Apr-2013 | 01-Feb-2013 | 01-May-2013 |
| Install Fixtures | 1 day | 01-Feb-2013 | 01-May-2013 | 04-Feb-2013 | 02-May-2013 |
| Connect Appliances | 1 day | 08-Mar-2013 | 02-May-2013 | 11-Mar-2013 | 03-May-2013 |
| Hardware | | 15-Apr-2013 | 17-Apr-2013 | 06-May-2013 | 06-May-2013 |
| Door Hardware | 2 days | 15-Apr-2013 | 01-May-2013 | 17-Apr-2013 | 03-May-2013 |
| Bath Hardware | 2 days | 15-Apr-2013 | 17-Apr-2013 | 17-Apr-2013 | 19-Apr-2013 |
| Mirrors | 5 days | 17-Apr-2013 | 26-Apr-2013 | 24-Apr-2013 | 03-May-2013 |
| Shower Doors | 10 days | 17-Apr-2013 | 19-Apr-2013 | 01-May-2013 | 03-May-2013 |
| Final Building Inspection | 0 days | 02-May-2013 | 03-May-2013 | 02-May-2013 | 03-May-2013 |
| Use & Occupancy Certificate | 0 days | 06-May-2013 | 06-May-2013 | 06-May-2013 | 06-May-2013 |
| First Walk-thru | 0 days | 06-May-2013 | 06-May-2013 | 06-May-2013 | 06-May-2013 |
| Final Punch-out | | 06-May-2013 | 06-May-2013 | 17-May-2013 | 17-May-2013 |
| Punch Out Walk-thru List | 4 days | 06-May-2013 | 06-May-2013 | 10-May-2013 | 10-May-2013 |
| Trim and Adjust Doors | 2 days | 10-May-2013 | 10-May-2013 | 14-May-2013 | 14-May-2013 |
| Paint Touch-up | 3 days | 14-May-2013 | 14-May-2013 | 17-May-2013 | 17-May-2013 |
| Cleaning | | 15-Apr-2013 | 06-May-2013 | 17-May-2013 | 17-May-2013 |
| Windows | 3 days | 15-Apr-2013 | 06-May-2013 | 18-Apr-2013 | 09-May-2013 |
| Rough Clean | 3 days | 18-Apr-2013 | 09-May-2013 | 23-Apr-2013 | 14-May-2013 |
| Final Clean | 2 days | 14-May-2013 | 14-May-2013 | 16-May-2013 | 16-May-2013 |
| Final Walk-through | 0 days | 16-May-2013 | 16-May-2013 | 16-May-2013 | 16-May-2013 |
| Move-in | 0 days | 17-May-2013 | 17-May-2013 | 17-May-2013 | 17-May-2013 |