| | Task Name | Duration | Start | Finish | Cost | Resources |
| Legal Work | | 15-Jul-2004 | 16-Jul-2004 | 1000 | |
| Sign Contracts | 1 day | 15-Jul-2004 | 16-Jul-2004 | 1000 | Lawyer |
| Physical Work | | 16-Jul-2004 | 09-Dec-2004 | 22379 | |
| Pre Construction | | 16-Jul-2004 | 23-Jul-2004 | 2879 | |
| Assemble Crews | 5 days | 16-Jul-2004 | 23-Jul-2004 | 1799 | Foreman[0.60] |
| Assemble Equipment | 3 days | 16-Jul-2004 | 21-Jul-2004 | 1080 | Foreman[0.60] |
| Construction | | 23-Jul-2004 | 09-Dec-2004 | 19500 | |
| Excavate | 6 days | 23-Jul-2004 | 02-Aug-2004 | 7200 | Foreman[0.50], Digging Machine, Truck[0.50], Labourer[3.00] |
| Lay Pipe | 6 days | 26-Jul-2004 | 03-Aug-2004 | 6600 | Foreman[0.50], Labourer[2.00], Welder, Truck[0.50] |
| Backfill | 6 days | 27-Jul-2004 | 04-Aug-2004 | 4200 | Labourer, Foreman |
| Landscape the ROW | 5 days | 02-Dec-2004 | 09-Dec-2004 | 1500 | Gardener[2.00] |
|